2016 ASD Bond- Update

In 2016, the voters in Alpine School District voted to pass a $387 million dollar bond that would facilitate construction of new schools throughout the district while also providing funds for property purchases (for future schools) and remodeling and rebuilding of several existing facilities. At the time, budgeted amounts for those projects were forecasted with our best estimates of what the construction costs would be.
 
Over the last four years, there has been a significant increase in the cost of land and also in construction costs.  This is an unprecedented increase, and we did not budget for this much of an increase.  Because of this, several of our projects have gone over budget.

The last phase of the bond, for $73 million is due to begin in January 2020.  Because of the increase in costs, nearly $33 million of those funds will need to be used to finish current projects.  This means that we will not have the money to be able to complete all of the projects that were supposed to be in the fourth phase, with $40 million remaining.  On August 1, 2019, we had a lengthy study session where we discussed this shortage and what we could do about it.  

This last spring, we sent out a survey to our patrons to ask several questions.  The questions asked solicited input from patrons on many subjects: Satisfaction with their school, teachers and administrators and ideas for how to deal with growth were among them.  One message from our patrons was very clear:  Consider all options before increasing taxes.  

Because of this input, on August 1st we also discussed the possibility of changing the format of our High Schools to be 9-12 grades instead of 10-12 grades.  We had hoped that this possibility would allow us to save some money in construction costs, while also positively impacting educational outcomes for our secondary students.  Research was inconclusive about the academic advantages provided by the 9-12 vs 10-12 models.  Feedback was solicited from the schools who are currently using the 9-12 or 7-8 models.  The feedback was overwhelmingly positive.  But we also discussed that feedback from the schools that are on a 7-9 or 10-12 model would also likely be positive.  Forecasting farther in the future indicated that while there would be a short term construction cost savings by switching the 9th graders to the High Schools, as we would need fewer new Jr High Schools, but that we would need new High Schools more quickly, so the savings would be negated in the long run.

I don't thing that this idea will be pursued at this point.  It is possible that individual schools will continue to employ the 9-12 model for various reasons, but I don't think that we will be moving to that model as a district.  But we ARE going to need to have some hard conversations about other alternative options that will allow us to maximize the space we currently have, and follow the input given by our taxpayers- to explore all options.

A newspaper article that came out after the meeting reported on the bond discussion, but some critical information was incomplete.  First, the article indicated that the entire amount of the 4th phase, $73 million, was the amount of the shortfall.  This is inaccurate.  The shortfall is approximately $33 million, a little less than half of the 4th phase total amount.  

Another piece of incomplete information in the article was a graph that indicated the amounts that some of the projects had cost- and that they were anywhere from approximately 10% over budget to more than double the original budget.  These amounts are the actual/anticipated costs of the projects, but what was not indicated was that we have additional funding sources available for some of them.  For example, rebuilding Central Elementary was included on Phase 3 of the bond.  The decision has been made to add a planetarium to the space center at Central Elementary.  This has increased the scope, and therefore the cost, of the project.  However, the difference in cost by adding the Planetarium will be entirely covered by donations.  So the entire amount that is shown in the article is not all coming from bond funds.  

The problem now is what to do.  We could employ various other methods to finance the needed buildings and still build all three schools (two elementary schools and one middle school).  We could also only build the middle school or only the two elementary schools.  Or some combination of those.  This is something that we will still need to discuss.  I feel a responsibility to our taxpayers for the promises that have been made to them: two elementary schools in high growth areas and a middle school in Lehi.  But I'm not sure how to do that with the funds remaining. Alpine School District has always followed through on the promises made to the public when a bond has been passed.  I don't want to be on the first board to break that streak.  

Link to article: HERE 

Projects that increased in budget: 
Property purchase prices increased significantly for all purchases
Cedar Valley High School: $73 million/ $79.9 million
Brookhaven Elementary: $16.5 million/$18.7 million
Belmont Elementary- approx. $2 million over projections
Mountain View High School (renovation): $6 million/$8.7 million
Liberty Hills Elementary: $17.2 million/ $19 million
Lake Mountain Middle School: $40 million/$48.2 million